INSTALATION 2,000 METERS OF HYDRAULIC BEAM MOULDS

  • Production capacity: 30,000 apartments in 2 years. Design of Factory lay-out. Custom made design of moulds and accessories (notch boxes and corbels).
  • Planning of logistics process: design, production, transport, commissioning in 5 months. On site production plant.